Deputy Minister of Transport: Inspection of Bac Giang Lang Son Highway
27/12/2017On the morning of 10 November, Deputy Minister of Transport Nguyen Van Cong led the mission of the Ministry to work with BOT Bac Giang – Lang Son Joint Stock Company and contractors to execute this project.
This project has just been restarted in the middle of this year and is currently under construction to meet the schedule at the end of 2019.
The project has a total investment of VND12,188 billion invested by BOT Bac Giang – Lang Son Joint Stock Company in the form of a BOT contract.
Km 45 + 100 (connecting Highway 1, Sao Mai, Chi Lang, Lang Son), the last point Km108 + 500, connecting to the end of the National Highway 1 Ha Giang – Bac Giang. Total length of the highway is 63.86 Km.
As expected, the project will complete component QL1 before 31/12/2017 and the high speed component will be completed before 31/12/2019. In order to ensure the time, the site clearance work must be completed by the end of this year.
This is an important project, besides servicing economic development, strengthening the connection with China, this project is also expected by localities. However, during the implementation process, the project was delayed, did not guarantee the urgent need in public opinion, as well as affect the trust of the local where the project passes. The main reason for the delay was due to the prestige and financial capacity of the previous investors, which was not enough to fund the project.
Representative of Bac Giang-Lang Son expressway project, Mr. Tran Phuc Tu reported to the Deputy Minister on the implementation of the project. In particular, ground clearance for the project component has been completed 44 / 64km, is expected to complete 100% of the site clearance by the end of this year.
At the project site, Vice Minister of Transport Nguyen Van Cong appreciated the efforts of investors. “This is a project that has just been restarted in the middle of this year, after the old investor did not meet the financial requirements, so we had to replace the new investor.”
“The investor needs to coordinate well with the two localities where the project passes through Bac Giang and Lang Son provinces, avoiding damage to investors, The BOT toll stations shall be set up according to the already calculated plans on the basis of agreement with localities. ”
Below are pictures of the inspection by Deputy Minister of Transportation Nguyen Van Cong at the Bac Giang – Lang Son expressway project:
Mr. Tran Phuc Tu General Director of BOT Bac Giang – Lang Son Joint Stock Company reported on the implementation of the project with Vice Minister of Transport Nguyen Van Cong.
Deputy Minister Nguyen Van Cong reviewed the project location on the map with Assoc
The project will be implemented from 2015-2018 and at the request of the Government, it must complete before 2020 the whole highway from Hanoi to Huu Nghi (Lang Son)
This project has a total investment of VND12.188 billion, invested by BOT Bac Giang – Lang Son Joint Stock Company in the form of a BOT contract.
The route began to show that the investor had poured all resources into the Bac Giang-Lang Son expressway project
Level training at Km93 area Huu Lung district, Lang Son
This is a new project that was resumed in June of 1977
Deputy Minister of Transport Nguyen Van Cong appreciated the efforts of the project owner
As expected, the project will complete component QL1 before 31/12/2017 and the high speed component will be completed before 31/12/2019.
According to Nhan Ha